Question 45

PIMCQ2 marksNeeds review
There are four locations (P, Q, R, S) and four factors to be considered for setting up a facility. The scores (on a scale of 0 to 10, with 10 being the maximum) for the given locations and the weight assigned to each factor are given as
Factor
Weight
P
Q
R
S
Availability of raw material
0.4
6
8
5
4
Availability of skilled labor
0.3
7
4
10
6
Infrastructure
0.2
8
3
10
8
Proximity to market
0.1
10
8
7
5
The best location for setting up the facility is
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

EXPLORE & PRACTISE

Paper and topic context

See where this question comes from and choose what to practise next.

2023PI

GATE PI 2023 · Paper 1

Production and Industrial Engineering · Original paper archive

Section
Production and Industrial Engineering
Question type
Multiple choice (MCQ)
Marks
2 marks

Practise related topics

Explore more previous year questions using this question’s imported topic tags.

production engineering

GATE PI previous year questions

industrial engineering

GATE PI previous year questions

manufacturing

GATE PI previous year questions

facility design

GATE PI previous year questions

Comments

Ask a question, share your approach, or help someone understand.

Log in to view the discussion

You’re not logged in. Log in or create an account to see discussions and add comments.