Questions 361–370 of 650. Imported answers require independent review unless marked reviewed.

Topic practice 650 questionsPage 37 of 65

Question 26

Open question
PIMCQ2 marksNeeds review
For a given process control chart, there are four rules for determining out-of-control state of the process which are being used simultaneously. The probability of Type-I error for the four rules are 0.005, 0.02, 0.03, and 0.05. Assuming independence of the rules, the probability of overall Type-I error when all the four rules are used simultaneously is
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 27

Open question
PIMCQ2 marksNeeds review
An in-control process has an estimated standard deviation of 2 mm. The specification limits of the component being processed are 120 ± 8 mm. When the process mean shifts to 118 mm, the values of the process capability indices,

and

, respectively, are,
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 28

Open question
PIMCQ2 marksNeeds review
There are a number of identical components in a parallel system. When the system reliability is 0.97 and the reliability of each individual component is 0.68, the number of identical components in the system is (if actual value is a fraction, it may be rounded up to the next higher integer).
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 29

Open question
PIMCQ2 marksNeeds review
A retail chain company has identified four sites A, B, C and D to open a new retail store. The company has selected four factors as the basis for evaluation of these sites. The factors, their weights, and the score for each site are given in the following table.
Factor
Factor weight
Score for site (out of 100): A
B
C
D
Average community income
0.4
60
70
80
50
Demand growth potential
0.1
30
80
50
40
Proximity to existing store
0.3
50
10
40
60
Availability of public transport
0.2
40
30
40
20
The site that should be selected to open the new retail store is
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 30

Open question
PIMCQ2 marksNeeds review
In the classical economic order quantity (EOQ) model, let

and

denote the optimal order quantity and the corresponding minimum total annual cost (the sum of the inventory holding and ordering costs). If the order quantity is estimated incorrectly as

, then the corresponding total annual cost

is
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 31

Open question
PIMCQ2 marksNeeds review
The eigenvalues of matrix

are 5 and 10. For matrix

, where

is a constant and

is a 2×2 identity matrix, its eigenvalues are
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 32

Open question
PIMCQ2 marksNeeds review
A company manufactures two products P and Q with unit profit of 4 and 5, respectively. The production requires manpower and two kinds of raw materials R1 and R2. The following table summarizes the requirement and availability of resources.
Resource
Resource usage per unit of production P
Q
Amount of resource available
manpower
1
1
10
R1
1
2
18
R2
2
1
18
The maximum profit the company can make is
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 33

Open question
PIMCQ2 marksNeeds review
A tool of an NC machine has to move along a circular arc from (20,20) to (10,10), while performing an operation. The center of the arc is at (20,10). Which one of the following NC tool commands performs the above mentioned operation?
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 34

Open question
PIMCQ2 marksNeeds review
In a shaft-hole assembly, the hole is specified as 30^_ mm. The mating shaft has a clearance fit with minimum clearance of 0.01 mm. The tolerance on the shaft is 0.03 mm. The maximum clearance in mm between the hole and the shaft is
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 35

Open question
PIMCQ2 marksNeeds review
‘GO’ and ‘NO GO’ snap gauges are to be designed for a shaft 36.000^_ mm. Gauge tolerance can be taken as 5% of the hole tolerance. Following the ISO system of gauge design, the respective sizes of ‘GO’ and ‘NO GO’ gauges are
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer