Question 40

Open question
PINAT2 marksNeeds review
The potential production alternatives for manufacturing a product along with their unit cost and monthly capacity are given in the Table.
S. No.
Production Alternatives
Unit cost (Rs.)
Capacity / month
1
Regular time production
5
300
2
Overtime production
6
200
3
Subcontracting
10
500
The inventory at the end of July is 100 units. If the demand for the month of August is 620, then the minimum total cost (in Rs.) to meet the demand is

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 55

Open question
PIMCQ2 marksNeeds review
In a gear manufacturing company, three orders P, Q and R are to be processed on a hobbing machine. The orders were received in the sequence P – Q – R. The Table indicates the process time remaining and production calendar due date for each order.
Order
Process Time Remaining (day)
Due date
P
4
Day 20
Q
16
Day 30
R
6
Day 19
Considering today as the Day 10 in the production calendar of the Hobbing Shop, the sequence of the orders scheduled using the ‘Critical Ratio’ rule is
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer