In a gear manufacturing company, three orders P, Q and R are to be processed on a hobbing machine. The orders were received in the sequence P – Q – R. The Table indicates the process time remaining and production calendar due date for each order.
Order | Process Time Remaining (day) | Due date |
|---|---|---|
P | 4 | Day 20 |
Q | 16 | Day 30 |
R | 6 | Day 19 |
Considering today as the Day 10 in the production calendar of the Hobbing Shop, the sequence of the orders scheduled using the ‘Critical Ratio’ rule is
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerEXPLORE & PRACTISE
Paper and topic context
See where this question comes from and choose what to practise next.
2017PI
GATE PI 2017 · Paper 1
Production and Industrial Engineering · Original paper archive
- Section
- Production and Industrial Engineering
- Question type
- Multiple choice (MCQ)
- Marks
- 2 marks
Practise related topics
Explore more previous year questions using this question’s imported topic tags.
production engineering
GATE PI previous year questions
industrial engineering
GATE PI previous year questions
manufacturing
GATE PI previous year questions
production control
GATE PI previous year questions
Comments
Ask a question, share your approach, or help someone understand.
Log in to view the discussion
You’re not logged in. Log in or create an account to see discussions and add comments.