Question 55

PIMCQ2 marksNeeds review
In a gear manufacturing company, three orders P, Q and R are to be processed on a hobbing machine. The orders were received in the sequence P – Q – R. The Table indicates the process time remaining and production calendar due date for each order.
Order
Process Time Remaining (day)
Due date
P
4
Day 20
Q
16
Day 30
R
6
Day 19
Considering today as the Day 10 in the production calendar of the Hobbing Shop, the sequence of the orders scheduled using the ‘Critical Ratio’ rule is
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

EXPLORE & PRACTISE

Paper and topic context

See where this question comes from and choose what to practise next.

2017PI

GATE PI 2017 · Paper 1

Production and Industrial Engineering · Original paper archive

Section
Production and Industrial Engineering
Question type
Multiple choice (MCQ)
Marks
2 marks

Practise related topics

Explore more previous year questions using this question’s imported topic tags.

production engineering

GATE PI previous year questions

industrial engineering

GATE PI previous year questions

manufacturing

GATE PI previous year questions

production control

GATE PI previous year questions

Comments

Ask a question, share your approach, or help someone understand.

Log in to view the discussion

You’re not logged in. Log in or create an account to see discussions and add comments.