Production and Industrial Engineering
GATE PI topic:project-management PYQs
Build your understanding with focused practice from past exam papers.
How to practice topic:project-management
Attempt a question, record the concept and assumptions, then check the available answer. Rework mistakes after revising the relevant concepts. Topic tags can overlap; review the question context.
Questions 1–10 of 10. Imported answers require independent review unless marked reviewed.
Question 24
Open questionPIMCQ1 markNeeds review
Painting is one of the activities in a construction project. For the painting activity that takes 6 days, both the total float and the free float are zero.
Which ONE of the following is TRUE for the painting activity?
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 41
Open questionPIMCQ2 marksNeeds review
The network diagram of eight activities (A to H) along with their time durations (in days, given in bracket) of a project is shown in the figure. The critical path of the project is

Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 41
Open questionPIMCQ2 marksNeeds review
A project has six activities and the precedence relationship among them is shown in the table.
Activity | Precedent activities |
|---|---|
A | None |
B | None |
C | None |
D | A, B |
E | B, C |
F | A, B |
The minimum number of dummy activities needed to draw an activity-on-arrow (AOA) representation of the project network is
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 53
Open questionPINAT2 marksNeeds review
Details of activities of a project are given as
Activity | A | B | C | D | E | F | G | H | I | J |
|---|---|---|---|---|---|---|---|---|---|---|
Time (days) | 8 | 10 | 8 | 7 | 16 | 15 | 18 | 14 | 9 | 4 |
Predecessors | - | - | - | A | A | B, D | C | C | F, G | E, I, H |
The time required, in days, to complete the project along the critical path is _____ (in integer).
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 35
Open questionPINAT1 markNeeds review
A project comprises of seven activities. The expected durations of activities and their variances are as follows:
Activity | Expected duration (minute) | Variance (minute) |
|---|---|---|
A | 4 | 1 |
B | 5 | 1 |
C | 4 | 1 |
D | 1 | 0 |
E | 7 | 4 |
F | 6 | 1 |
G | 8 | 4 |
The critical path consists of activities B, E and G. The standard deviation (in minute) of the project duration is____________. [round off to two decimal places]
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 42
Open questionPINAT2 marksNeeds review
A project consists of eight activities. The time required for each activity and its immediate predecessor(s) are given in the table below.
Activity | Activity time (in days) | Immediate predecessor(s) |
|---|---|---|
A | 2 | - |
B | 3 | - |
C | 2 | A |
D | 4 | A, B |
E | 4 | C |
F | 3 | C |
G | X | D, E |
H | 2 | F, G |
If the project completion time using critical path method (CPM) is 15 days, then the value of X (in days) is ________. [in integer]
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 50
Open questionPINAT2 marksNeeds review
A project consists of seven activities as listed in the table. The time required for each activity and its immediate predecessor(s) are also given.
Activity | Time required (in weeks) | Immediate Predecessor(s) |
|---|---|---|
P | 7 | - |
Q | 4 | - |
R | 2 | Q |
S | 11 | P |
T | 9 | P, R |
U | 9 | Q |
V | 4 | T, U |
The project completion time using Critical Path Method (CPM) in weeks is ____________.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 53
Open questionPINAT2 marksNeeds review
A PERT project network consists of 5 activities A to E. The time estimates of these activities follow Beta-distribution. The predecessor–successor (P-S) relationships between the nodes and time estimates of activities are given in table.
Activity | P-S | Optimistic time (days) | Most likely time (days) | Pessimistic time (days) |
|---|---|---|---|---|
A | 1–2 | 2 | 4 | 6 |
B | 2–3 | 4 | 5 | 12 |
C | 2–4 | 5 | 8 | 11 |
D | 3–5 | 2 | 5 | 08 |
E | 4–5 | 4 | 6 | 14 |
The variance (in days) of the critical path is ______ (round off to 2 decimal places)
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 43
Open questionPINAT2 marksNeeds review
A project consists of three activities P, Q and R. The durations of activities follow Beta distribution. The predecessors and durations of activities are as per the following table: | Activity | Predecessors | Optimistic time (month) | Most likely time (month) | Pessimistic time (month) | P | — | 2 | 3 | 10 | Q | P | 3 | 5 | 13 | R | Q | 3 | 4 | 5 | The expected project completion time (in month) is _____
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 39
Open questionPINAT2 marksNeeds review
In a project, tasks A, B, C, D, E, F, G, H, I and J are to be performed. The precedence relationships and the time required (in days) to complete the tasks are given in the Table.
Tasks | A | B | C | D | E | F | G | H | I | J |
|---|---|---|---|---|---|---|---|---|---|---|
Time (days) | 8 | 10 | 8 | 10 | 16 | 17 | 18 | 14 | 9 | 4 |
Preceding tasks | - | - | - | A | A | B, D | C | C | F, G | E, I, H |
The time required (in days) to complete the project along the critical path is
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer