Question 24

Open question
PIMCQ1 markNeeds review
Painting is one of the activities in a construction project. For the painting activity that takes 6 days, both the total float and the free float are zero.
Which ONE of the following is TRUE for the painting activity?
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 41

Open question
PIMCQ2 marksNeeds review
The network diagram of eight activities (A to H) along with their time durations (in days, given in bracket) of a project is shown in the figure. The critical path of the project is
Diagram for Production and Industrial Engineering question 41

Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 41

Open question
PIMCQ2 marksNeeds review
A project has six activities and the precedence relationship among them is shown in the table.
Activity
Precedent activities
A
None
B
None
C
None
D
A, B
E
B, C
F
A, B
The minimum number of dummy activities needed to draw an activity-on-arrow (AOA) representation of the project network is
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 53

Open question
PINAT2 marksNeeds review
Details of activities of a project are given as
Activity
A
B
C
D
E
F
G
H
I
J
Time (days)
8
10
8
7
16
15
18
14
9
4
Predecessors
-
-
-
A
A
B, D
C
C
F, G
E, I, H
The time required, in days, to complete the project along the critical path is _____ (in integer).

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 35

Open question
PINAT1 markNeeds review
A project comprises of seven activities. The expected durations of activities and their variances are as follows:
Activity
Expected duration (minute)
Variance (minute)
A
4
1
B
5
1
C
4
1
D
1
0
E
7
4
F
6
1
G
8
4
The critical path consists of activities B, E and G. The standard deviation (in minute) of the project duration is____________. [round off to two decimal places]

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 42

Open question
PINAT2 marksNeeds review
A project consists of eight activities. The time required for each activity and its immediate predecessor(s) are given in the table below.
Activity
Activity time (in days)
Immediate predecessor(s)
A
2
-
B
3
-
C
2
A
D
4
A, B
E
4
C
F
3
C
G
X
D, E
H
2
F, G
If the project completion time using critical path method (CPM) is 15 days, then the value of X (in days) is ________. [in integer]

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 50

Open question
PINAT2 marksNeeds review
A project consists of seven activities as listed in the table. The time required for each activity and its immediate predecessor(s) are also given.
Activity
Time required (in weeks)
Immediate Predecessor(s)
P
7
-
Q
4
-
R
2
Q
S
11
P
T
9
P, R
U
9
Q
V
4
T, U
The project completion time using Critical Path Method (CPM) in weeks is ____________.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 53

Open question
PINAT2 marksNeeds review
A PERT project network consists of 5 activities A to E. The time estimates of these activities follow Beta-distribution. The predecessor–successor (P-S) relationships between the nodes and time estimates of activities are given in table.
Activity
P-S
Optimistic time (days)
Most likely time (days)
Pessimistic time (days)
A
1–2
2
4
6
B
2–3
4
5
12
C
2–4
5
8
11
D
3–5
2
5
08
E
4–5
4
6
14
The variance (in days) of the critical path is ______ (round off to 2 decimal places)

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 43

Open question
PINAT2 marksNeeds review
A project consists of three activities P, Q and R. The durations of activities follow Beta distribution. The predecessors and durations of activities are as per the following table: | Activity | Predecessors | Optimistic time (month) | Most likely time (month) | Pessimistic time (month) | P | — | 2 | 3 | 10 | Q | P | 3 | 5 | 13 | R | Q | 3 | 4 | 5 | The expected project completion time (in month) is _____

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 39

Open question
PINAT2 marksNeeds review
In a project, tasks A, B, C, D, E, F, G, H, I and J are to be performed. The precedence relationships and the time required (in days) to complete the tasks are given in the Table.
Tasks
A
B
C
D
E
F
G
H
I
J
Time (days)
8
10
8
10
16
17
18
14
9
4
Preceding tasks
-
-
-
A
A
B, D
C
C
F, G
E, I, H
The time required (in days) to complete the project along the critical path is

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer