GATE PI · 2017 · PI
Question 39: Project management
Give it a try, then reveal the answer to check your work.
Question 39
PINAT2 marksNeeds review
In a project, tasks A, B, C, D, E, F, G, H, I and J are to be performed. The precedence relationships and the time required (in days) to complete the tasks are given in the Table.
Tasks | A | B | C | D | E | F | G | H | I | J |
|---|---|---|---|---|---|---|---|---|---|---|
Time (days) | 8 | 10 | 8 | 10 | 16 | 17 | 18 | 14 | 9 | 4 |
Preceding tasks | - | - | - | A | A | B, D | C | C | F, G | E, I, H |
The time required (in days) to complete the project along the critical path is
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerEXPLORE & PRACTISE
Paper and topic context
See where this question comes from and choose what to practise next.
2017PI
GATE PI 2017 · Paper 1
Production and Industrial Engineering · Original paper archive
- Section
- Production and Industrial Engineering
- Question type
- Numerical answer (NAT)
- Marks
- 2 marks
Practise related topics
Explore more previous year questions using this question’s imported topic tags.
production engineering
GATE PI previous year questions
industrial engineering
GATE PI previous year questions
manufacturing
GATE PI previous year questions
project management
GATE PI previous year questions