Question 64
Open questionMNNAT2 marksNeeds review
A wastewater sample has an ultimate BOD of 300 mg/L. BOD reaction rate constant is 0.22 per day at 20 °C. If the temperature coefficient is 1.05, the 5-day BOD at 25 °C, in mg/L, is ____ (rounded off to 2 decimal places)
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerQuestion 65
Open questionMNNAT2 marksNeeds review
A double ended range drum (DERD) shearer uni-directionally cuts coal in a longwall panel having the following details
Shearer drum diameter = 1.4 m
Panel dimension = 1200 m × 200 m × 2.4 m
Web depth = 0.6 m
Average cutting speed = 5 m/minute
Average retreating speed = 10 m/minute
Average operational delay between cuts is 2 hour. There are two production shifts, each of 8 hour duration. The number of days required for complete extraction of the panel is ____ (in integer)
Log in to check the answer