A project consists of six activities. The immediate predecessor of each activity and the estimated duration is also provided in the table below:
Activity | Immediate predecessor | Estimated duration (weeks) |
|---|---|---|
P | - | 5 |
Q | - | 1 |
R | Q | 2 |
S | P, R | 4 |
T | P | 6 |
U | S, T | 3 |
If all activities other than S take the estimated amount of time, the maximum duration (in weeks) of the activity S without delaying the completion of the project is __________
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerEXPLORE & PRACTISE
Paper and topic context
See where this question comes from and choose what to practise next.
2019ME
GATE ME 2019 · Paper 1
Mechanical Engineering · Original paper archive
- Section
- Mechanical Engineering
- Question type
- Numerical answer (NAT)
- Marks
- 2 marks
Practise related topics
Explore more previous year questions using this question’s imported topic tags.
mechanical engineering
GATE ME previous year questions
mechanics
GATE ME previous year questions
manufacturing
GATE ME previous year questions
operations research
GATE ME previous year questions
Comments
Ask a question, share your approach, or help someone understand.
Log in to view the discussion
You’re not logged in. Log in or create an account to see discussions and add comments.