Five jobs (J1, J2, J3, J4 and J5) need to be processed in a factory. Each job can be assigned to any of the five different machines (M1, M2, M3, M4 and M5). The time durations taken (in minutes) by the machines for each of the jobs, are given in the table. However, each job is assigned to a specific machine in such a way that the total processing time is minimum. The total processing time is ______ minutes.

M1
M2
M3
M4
M5
J1
40
30
50
50
58
J2
26
38
60
26
38
J3
40
34
28
24
30
J4
28
40
40
32
48
J5
28
32
38
22
44

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

EXPLORE & PRACTISE

Paper and topic context

See where this question comes from and choose what to practise next.

2019ME

GATE ME 2019 · Paper 1

Mechanical Engineering · Original paper archive

Section
Mechanical Engineering
Question type
Numerical answer (NAT)
Marks
2 marks

Practise related topics

Explore more previous year questions using this question’s imported topic tags.

mechanical engineering

GATE ME previous year questions

mechanics

GATE ME previous year questions

manufacturing

GATE ME previous year questions

operations research

GATE ME previous year questions

Comments

Ask a question, share your approach, or help someone understand.

Log in to view the discussion

You’re not logged in. Log in or create an account to see discussions and add comments.