Question 28: Production Planning and Control
Give it a try, then reveal the answer to check your work.
Question 28
MEMCQ2 marksNeeds review
A set of jobs A, B, C, D, E, F, G, H arrive at time
for processing on turning and grinding machines. Each job needs to be processed in sequence – first on the turning machine and second on the grinding machine, and the grinding must occur immediately after turning. The processing times of the jobs are given below.Job | A | B | C | D | E | F | G | H |
|---|---|---|---|---|---|---|---|---|
Turning (minutes) | 2 | 4 | 8 | 9 | 7 | 6 | 5 | 10 |
Grinding (minutes) | 6 | 1 | 3 | 7 | 9 | 5 | 2 | 4 |
If the makespan is to be minimized, then the optimal sequence in which these jobs must be processed on the turning and grinding machines is
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerEXPLORE & PRACTISE
Paper and topic context
See where this question comes from and choose what to practise next.
2021ME
GATE ME 2021 · Paper 1
Mechanical Engineering · Original paper archive
- Section
- Mechanical Engineering
- Question type
- Multiple choice (MCQ)
- Marks
- 2 marks
Practise related topics
Explore more previous year questions using this question’s imported topic tags.
mechanical engineering
GATE ME previous year questions
mechanics
GATE ME previous year questions
manufacturing
GATE ME previous year questions
production planning control
GATE ME previous year questions
Production Planning and Control
GATE ME previous year questions
Comments
Ask a question, share your approach, or help someone understand.
Log in to view the discussion
You’re not logged in. Log in or create an account to see discussions and add comments.