Question 47

Open question
MEMCQ2 marksNeeds review
Four jobs are on order in a factory. As on day 20 of the production calendar, the corresponding due date and work remaining to complete these jobs (in days) are given in the table below.
Job
Due date
Work remaining (in days)
M
26
5
N
24
10
O
28
10
P
31
5
Which job(s) has/have critical ratio less than unity?
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 60

Open question
MENAT2 marksNeeds review
The actual demand for castings in a factory is 500 units and 635 units for the months of January 2026 and February 2026, respectively. The forecasted demand for January 2026 is 250 units and smoothing constant is 0.7. Using the exponential smoothing method, the forecast of the demand for castings in March 2026 is ______ units (in integer).

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 37

Open question
MEMCQ2 marksNeeds review
Considering the actual demand and the forecast for a product given in the table below, the mean forecast error and the mean absolute deviation, respectively, are
Period
1
2
3
4
5
6
7
8
9
10
Actual demand
425
415
420
430
427
418
422
416
426
421
Forecast
427
422
416
422
423
420
419
418
430
415
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 34

Open question
MEMCQ1 markNeeds review
A set of jobs

arrive at time

to a production line consisting of two workstations in series. Each job must be processed by both workstations in sequence (i.e., the first followed by the second). The process times (in minutes) for each job on each workstation in the production line are given below.
Job






Workstation 1
5
7
3
4
6
8
Workstation 2
4
6
6
8
5
7
The sequence in which the jobs must be processed by the production line if the total makespan of production is to be minimized is
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 32

Open question
MENAT1 markNeeds review
An electric car manufacturer underestimated the January sales of car by 20 units, while the actual sales was 120 units. If the manufacturer uses exponential smoothing method with a smoothing constant of

, then the sales forecast for the month of February of the same year is ______ units (in integer).

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 59

Open question
MENAT2 marksNeeds review
The product structure diagram shows the number of different components required at each level to produce one unit of the final product P. If there are 50 units of on-hand inventory of component A, the number of additional units of component A needed to produce 10 units of product P is ________ (in integer).
Diagram for Mechanical Engineering question 59


Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 28

Open question
MEMCQ2 marksNeeds review
A set of jobs A, B, C, D, E, F, G, H arrive at time

for processing on turning and grinding machines. Each job needs to be processed in sequence – first on the turning machine and second on the grinding machine, and the grinding must occur immediately after turning. The processing times of the jobs are given below.
Job
A
B
C
D
E
F
G
H
Turning (minutes)
2
4
8
9
7
6
5
10
Grinding (minutes)
6
1
3
7
9
5
2
4
If the makespan is to be minimized, then the optimal sequence in which these jobs must be processed on the turning and grinding machines is
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 29

Open question
MEMCQ2 marksNeeds review
A factory produces

(

) products, each of which requires processing on

(

) workstations. Let

be the amount of processing time that one unit of the

product requires on the

workstation. Let the revenue from selling one unit of the

product be

and

be the holding cost per unit per time period for the

product. The planning horizon consists of

(

) time periods. The minimum demand that must be satisfied in time period

is

and the capacity of the

workstation in time period

is

. Consider the aggregate planning formulation below, with decision variables

(amount of product

sold in time period

),

(amount of product

manufactured in time period

) and

(amount of product

held in inventory at the end of time period

).

The capacity constraints and inventory balance constraints for this formulation are
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 43

Open question
MENAT2 marksNeeds review
The demand and forecast of an item for five months are given in the table.
Month
Demand
Forecast
April
225
200
May
220
240
June
285
300
July
290
270
August
250
230
The Mean Absolute Percent Error (MAPE) in the forecast is __________ % (round off to two decimal places)

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 13

Open question
MEMCQ1 markNeeds review
In Materials Requirement Planning, if the inventory holding cost is very high and the setup cost is zero, which one of the following lot sizing approaches should be used?
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer