Question 47: Production Planning and Control
Give it a try, then reveal the answer to check your work.
Question 47
MEMCQ2 marksNeeds review
Four jobs are on order in a factory. As on day 20 of the production calendar, the corresponding due date and work remaining to complete these jobs (in days) are given in the table below.
Job | Due date | Work remaining (in days) |
|---|---|---|
M | 26 | 5 |
N | 24 | 10 |
O | 28 | 10 |
P | 31 | 5 |
Which job(s) has/have critical ratio less than unity?
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerEXPLORE & PRACTISE
Paper and topic context
See where this question comes from and choose what to practise next.
2026ME
GATE ME 2026 · Paper 1
Mechanical Engineering · Original paper archive
- Section
- Mechanical Engineering
- Question type
- Multiple choice (MCQ)
- Marks
- 2 marks
Practise related topics
Explore more previous year questions using this question’s imported topic tags.
mechanical engineering
GATE ME previous year questions
mechanics
GATE ME previous year questions
manufacturing
GATE ME previous year questions
production planning control
GATE ME previous year questions
Production Planning and Control
GATE ME previous year questions
Comments
Ask a question, share your approach, or help someone understand.
Log in to view the discussion
You’re not logged in. Log in or create an account to see discussions and add comments.