Question 34

MEMCQ1 markNeeds review
A set of jobs

arrive at time

to a production line consisting of two workstations in series. Each job must be processed by both workstations in sequence (i.e., the first followed by the second). The process times (in minutes) for each job on each workstation in the production line are given below.
Job






Workstation 1
5
7
3
4
6
8
Workstation 2
4
6
6
8
5
7
The sequence in which the jobs must be processed by the production line if the total makespan of production is to be minimized is
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

EXPLORE & PRACTISE

Paper and topic context

See where this question comes from and choose what to practise next.

2024ME

GATE ME 2024 · Paper 1

Mechanical Engineering · Original paper archive

Section
Mechanical Engineering
Question type
Multiple choice (MCQ)
Marks
1 mark

Practise related topics

Explore more previous year questions using this question’s imported topic tags.

mechanical engineering

GATE ME previous year questions

mechanics

GATE ME previous year questions

manufacturing

GATE ME previous year questions

production planning control

GATE ME previous year questions

Production Planning and Control

GATE ME previous year questions

Comments

Ask a question, share your approach, or help someone understand.

Log in to view the discussion

You’re not logged in. Log in or create an account to see discussions and add comments.