Question 48

MNNAT2 marksNeeds review
In a level terrain, a vertical orebody of 20 m uniform width is worked by surface mining method. The density of the ore is 2.5 tonne/m

. The ultimate pit has a depth of 60 m, width of 20 m at pit bottom, and a pit slope of 45°. The overall stripping ratio for this condition in m

/tonne is ____________________.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

EXPLORE & PRACTISE

Paper and topic context

See where this question comes from and choose what to practise next.

2018MN

GATE MN 2018 · Paper 1

Mining Engineering · Original paper archive

Section
Mining Engineering
Question type
Numerical answer (NAT)
Marks
2 marks

Practise related topics

Explore more previous year questions using this question’s imported topic tags.

mining engineering

GATE MN previous year questions

mining

GATE MN previous year questions

mineral processing

GATE MN previous year questions

mine planning

GATE MN previous year questions

mining methods

GATE MN previous year questions

surface mining

GATE MN previous year questions

Comments

Ask a question, share your approach, or help someone understand.

Log in to view the discussion

You’re not logged in. Log in or create an account to see discussions and add comments.