GATE AR · 2017 · AR
Question 18: Construction and Management
Give it a try, then reveal the answer to check your work.
Question 18
ARMCQ1 markNeeds review
In which of the following models does the private partner own the revenue as well as the risk associated with the project for a limited period of time?
Your answerChoose one option.
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerEXPLORE & PRACTISE
Paper and topic context
See where this question comes from and choose what to practise next.
2017AR
GATE AR 2017 · Paper 1
Architecture and Planning · Original paper archive
- Section
- Architecture and Planning
- Question type
- Multiple choice (MCQ)
- Marks
- 1 mark
Practise related topics
Explore more previous year questions using this question’s imported topic tags.
architecture
GATE AR previous year questions
urban planning
GATE AR previous year questions
built environment
GATE AR previous year questions
construction management
GATE AR previous year questions
Construction and Management
GATE AR previous year questions
Comments
Ask a question, share your approach, or help someone understand.
Log in to view the discussion
You’re not logged in. Log in or create an account to see discussions and add comments.