Question 52: Production Planning and Control
Give it a try, then reveal the answer to check your work.
Question 52
MENAT2 marksNeeds review
Processing times (including setup times) and due dates for six jobs waiting to be processed at a work centre are given in the table. The average tardiness (in days) using shortest processing time rule is ________ (correct to two decimal places).
Job | Processing time (days) | Due date (days) |
|---|---|---|
A | 3 | 8 |
B | 7 | 16 |
C | 4 | 4 |
D | 9 | 18 |
E | 5 | 17 |
F | 13 | 19 |
Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerEXPLORE & PRACTISE
Paper and topic context
See where this question comes from and choose what to practise next.
2018ME
GATE ME 2018 · Paper 1
Mechanical Engineering · Original paper archive
- Section
- Mechanical Engineering
- Question type
- Numerical answer (NAT)
- Marks
- 2 marks
Practise related topics
Explore more previous year questions using this question’s imported topic tags.
mechanical engineering
GATE ME previous year questions
mechanics
GATE ME previous year questions
manufacturing
GATE ME previous year questions
production planning control
GATE ME previous year questions
Production Planning and Control
GATE ME previous year questions
Comments
Ask a question, share your approach, or help someone understand.
Log in to view the discussion
You’re not logged in. Log in or create an account to see discussions and add comments.