Robot Ltd. wishes to maintain enough safety stock during the lead time period between starting a new production run and its completion such that the probability of satisfying the customer demand during the lead time period is 95%. The lead time period is 5 days and daily customer demand can be assumed to follow the Gaussian (normal) distribution with mean 50 units and a standard deviation of 10 units. Using
, where
represents the cumulative distribution function of the standard normal random variable, the amount of safety stock that must be maintained by Robot Ltd. to achieve this demand fulfilment probability for the lead time period is ______ units (round off to two decimal places).Log in to check the answer
You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answerEXPLORE & PRACTISE
Paper and topic context
See where this question comes from and choose what to practise next.
2021ME
GATE ME 2021 · Paper 1
Mechanical Engineering · Original paper archive
- Section
- Mechanical Engineering
- Question type
- Numerical answer (NAT)
- Marks
- 1 mark
Practise related topics
Explore more previous year questions using this question’s imported topic tags.
mechanical engineering
GATE ME previous year questions
mechanics
GATE ME previous year questions
manufacturing
GATE ME previous year questions
inventory control
GATE ME previous year questions
Comments
Ask a question, share your approach, or help someone understand.
Log in to view the discussion
You’re not logged in. Log in or create an account to see discussions and add comments.