Question 37

CENAT2 marksNeeds review
The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of all the activities are shown in the table. The indirect cost incurred by the contractor is INR 500 per day. If the project is targeted for completion in 16 days, the total cost (in INR) to be incurred by the contractor would be ________.
Diagram for Civil Engineering question 37


Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

EXPLORE & PRACTISE

Paper and topic context

See where this question comes from and choose what to practise next.

2019CE

GATE CE 2019 · Paper 1

Civil Engineering · Original paper archive

Section
Civil Engineering
Question type
Numerical answer (NAT)
Marks
2 marks

Practise related topics

Explore more previous year questions using this question’s imported topic tags.

civil engineering

GATE CE previous year questions

infrastructure

GATE CE previous year questions

structural engineering

GATE CE previous year questions

construction materials management

GATE CE previous year questions

Construction Materials and Management

GATE CE previous year questions

Comments

Ask a question, share your approach, or help someone understand.

Log in to view the discussion

You’re not logged in. Log in or create an account to see discussions and add comments.