Questions 21–30 of 30. Imported answers require independent review unless marked reviewed.

Topic practice 30 questionsPage 3 of 3

Question 54

Open question
MENAT2 marksNeeds review
Five jobs (J1, J2, J3, J4 and J5) need to be processed in a factory. Each job can be assigned to any of the five different machines (M1, M2, M3, M4 and M5). The time durations taken (in minutes) by the machines for each of the jobs, are given in the table. However, each job is assigned to a specific machine in such a way that the total processing time is minimum. The total processing time is ______ minutes.

M1
M2
M3
M4
M5
J1
40
30
50
50
58
J2
26
38
60
26
38
J3
40
34
28
24
30
J4
28
40
40
32
48
J5
28
32
38
22
44

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 55

Open question
MENAT2 marksNeeds review
A project consists of six activities. The immediate predecessor of each activity and the estimated duration is also provided in the table below:
Activity
Immediate predecessor
Estimated duration (weeks)
P
-
5
Q
-
1
R
Q
2
S
P, R
4
T
P
6
U
S, T
3
If all activities other than S take the estimated amount of time, the maximum duration (in weeks) of the activity S without delaying the completion of the project is __________

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 35

Open question
MEMCQ2 marksNeeds review
The problem of maximizing

subject to constraints

,

,

and

has
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 51

Open question
MENAT2 marksNeeds review
The minimum value of 3x + 5y such that: 3x + 5y ≤ 15 4x + 9y ≤ 8 13x + 2y ≤ 2 x ≥ 0, y ≥ 0
is ______.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 51

Open question
MENAT2 marksNeeds review
The arc lengths of a directed graph of a project are shown in the figure. The shortest path length from node 1 to node 6 is ______.
Diagram for Mechanical Engineering question 51


Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 23

Open question
ME-2MCQ1 markNeeds review
For a single server with Poisson arrival and exponential service time, the arrival rate is 12 per hour. Which one of the following service rates will provide a steady state finite queue length?
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 48

Open question
ME-2MCQ2 marksNeeds review
A product made in two factories, P and Q, is transported to two destinations, R and S. The per unit costs of transportation (in Rupees) from factories to destinations are as per the following matrix:
Factory
R
S
P
10
7
Q
3
4
Factory P produces 7 units and factory Q produces 9 units of the product. Each destination requires 8 units. If the north-west corner method provides the total transportation cost as

(in Rupees) and the optimized (the minimum) total transportation cost is

(in Rupees), then

, in Rupees, is
Your answerChoose one option.

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 49

Open question
ME-2NAT2 marksNeeds review
A project starts with activity A and ends with activity F. The precedence relation and durations of the activities are as per the following table:
Activity
Immediate predecessor
Duration (days)
A
–
4
B
A
3
C
A
7
D
B
14
E
C
4
F
D, E
9
The minimum project completion time (in days) is ____________

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 51

Open question
ME-1NAT2 marksNeeds review
Two models, P and Q, of a product earn profits of Rs. 100 and Rs. 80 per piece, respectively. Production times for P and Q are 5 hours and 3 hours, respectively, while the total production time available is 150 hours. For a total batch size of 40, to maximize profit, the number of units of P to be produced is ________

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer

Question 51

Open question
ME-2NAT2 marksNeeds review
Maximize

, subject to

,

,

. In the starting Simplex table,

and

are non-basic variables and the value of

is zero. The value of

in the next Simplex table is ____________

Log in to check the answer

You can attempt this question now. Sign in to view the answer key, explanations and discussion.Log in to check answer